Alberta requirements

Alberta ground disturbance rules

What Alberta's pipeline rules and OHS Code require before and during any digging, and where Ground Disturbance 201 fits in.

Last updated

What counts as a ground disturbance?

Alberta’s Pipeline Act defines ground disturbance broadly. It includes excavating, digging, trenching, plowing, drilling, tunnelling, blasting and grading. Cultivation less than 45 cm deep is excluded.

Alberta’s OHS Code (Part 32, section 441) uses a similar test: any work on or under the surface that disturbs or displaces soil. A few activities are excluded, including routine minor road maintenance and hand digging no deeper than 300 mm that doesn’t permanently remove cover over a buried facility.

Before you dig

The Alberta Energy Regulator (AER) says anyone planning a ground disturbance must:

  • search for pipelines for 30 metres beyond the entire perimeter of the planned dig area, and
  • contact Utility Safety Partners (formerly Alberta One-Call) at clickbeforeyoudig.com or 1-800-242-3447 to request locates of buried facilities.

Not every underground facility is registered with Utility Safety Partners, so don’t assume a clear search means nothing is there.

Locate marks (OHS Code, section 447)

Before disturbing the ground, the employer must contact the owner of any pipeline within 30 m of the work site, and of any other buried facility that may be affected. The employer must tell the owner what’s planned and ask them to mark the facility’s location. Ground can’t be disturbed until facilities have been identified and their locations marked.

Workers must be made aware of the locate marks. If the work moves or destroys the marks, they must be re-established.

Hand exposing (OHS Code, section 448)

Mechanical excavation equipment can’t be used within the hand expose zone of a buried facility until the facility has been exposed by hand digging, an owner-approved non-destructive method (such as hydrovac) or an equivalent method. Mechanical excavation within 600 mm of a buried pipeline isn’t allowed unless an owner’s representative directly supervises it.

Training and competency

The AER reminds licensees to make sure the people carrying out ground disturbance are trained and competent, and that their training is appropriate and current. In practice, most Alberta owners, prime contractors and municipalities ask for Ground Disturbance 201 for anyone planning or supervising the work, and Ground Disturbance 101 for workers on the ground.

Start Ground Disturbance 201 →

Sources: Alberta Energy Regulator, ground disturbance guidance and Bulletin 2023-30; Alberta OHS Code, Part 32, sections 441, 447 and 448. General guidance, not legal advice. Always check the current Pipeline Act, Pipeline Rules and OHS Code.